Heo Tae-soo: "Beyond the Sunrise, a Landmark for Seeing AI's Future"… GS Starts Construction of Donghae Data Center
Chips2 min read
GS Group has started building a large AI data center in Donghae, a city in Gangwon Province, South Korea. The first phase is 1.2 gigawatts (GW), part of a planned 2.4 GW project.
GS starts building an AI data center in Donghae
On the 28th, GS Group held a groundbreaking ceremony for a 1.2 GW AI data center in the Bukpyeong No. 2 industrial complex in Donghae. President Lee Jae-myung and GS chairman Huh Tae-soo attended. This is phase one of a 2.4 GW project, with an investment of 15 trillion won. The first 100 MW center is expected to finish in the second quarter of 2028. The rest will be built one after another, with full completion and operation by 2029.
Key numbers
- Phase one: 1.2 GW, with 700 MW on about 80,000 pyeong (about 265,000 square meters) of industrial land and 500 MW on extra land.
- Whole project: 2.4 GW, with about 30 trillion won in investment.
- Phase one investment: 15 trillion won.
- Total project value, including GPUs (graphics chips) and memory: up to 120 trillion won.
- Jobs: about 70,000 people in total during construction, and about 1,000 people to run the center.
How GS got here
In June, GS set up a new company called GS AI Infrastructure to handle the project. It combined GS's power and energy experience with the design and building skills of GS E&C. GS then signed agreements with Gangwon Province and Donghae City and finished required steps such as power grid impact review and building permits. The company says this is the first construction start among the GW-scale AI data centers in the government's 'Three Mega Projects for Korea's Great Leap Forward,' announced on June 29, about five months ago.
Why it matters
Data centers need huge amounts of electricity and chips to train and run AI. This project shows that Korean companies are willing to build very large AI infrastructure outside Seoul. GS also plans to expand to other regions using land it already owns. For local people, the project promises jobs and new chances for local companies, and the power cable was routed around a local market to address resident concerns.
What to watch
- Whether the first 100 MW center opens in the second quarter of 2028 as planned.
- Progress on the remaining phases, due by 2029.
- Which local companies win work, through the local growth council set up with Donghae City.
- Where GS builds next, using its other land.