AI Data Center Megaproject Kicks Off: GS Breaks Ground on 1.2GW Donghae Center
Policy2 min read
GS has started building a 1.2 gigawatt (GW) AI data center in Donghae, Gangwon Province. It is the first GW-scale AI data center in the government's mega project plan to begin construction.
GS starts building an AI data center in Donghae
GS began construction of a 1.2 GW artificial intelligence (AI) data center in Donghae City, Gangwon Province. The Ministry of Science and ICT held a groundbreaking ceremony on the 28th. This is the first phase of a 2.4 GW Donghae AI data center plan that GS announced in June. GS plans to finish the building in stages from 2028 and open it in 2029. GS also shared its plan for building, running, and growing the AI industry around the site, along with ways to help the local area.
Key numbers and facts
- Phase 1 size: 1.2 GW, out of a 2.4 GW total plan
- Target opening: 2029, with stages finished from 2028
- Local jobs after opening: several hundred to about 1,000 direct and indirect jobs expected
- Rule change: a 50 megawatt (MW) limit for skipping power grid impact reviews for data centers outside the Seoul area
- Local chip and parts share: about 10% today, which the government wants to raise
What is an AI data center?
An AI data center is a large building full of powerful computers. These computers train and run AI programs. Because they use huge amounts of electricity, they need a lot of power and land. The government has a special law for AI data centers, called the AIDC Industry Promotion Act, which takes effect next March. The law sets out support and faster permit rules.
Why it matters
This project shows that the government's mega project plan is moving from paper to real construction. It could bring jobs to the local area and help young people stay in their home regions. The government also wants to build more of the parts and tools for AI data centers in Korea, so the country depends less on other countries. The minister said the Donghae project should become a model for how big investments can help local communities.
What to watch
- Public comments on the new rules for the AIDC law, which were announced on the 20th
- Next year's research projects and test sites, and the regions chosen for clusters
- Whether the Donghae site is finished from 2028 and opens in 2029 as planned
- How many local residents are hired, and how the university training courses work
- Progress of the AIDC Alliance, which brings government, companies, and local groups together
Glossary
- GS
- A Korean company group that is building this AI data center in Donghae.
- AI data center
- A large building of computers that train and run artificial intelligence programs.
- AIDC
- Short for AI data center. It is the name used in the government law and plans.
- Ministry of Science and ICT
- The Korean government office in charge of science, technology, and information and communication.
- AIDC Alliance
- A group of government, data center companies, and parts makers that share ideas and help set policy.